The hull-mating work on the FPSO Gato do Mato, Shell's floating production unit destined for Brazilian waters, has been completed by MODEC, Inc., nearly a month ahead of schedule and with strong quality results, the company announced.

The vessel holds particular significance for MODEC as the first of its floating production units to have hull sections built simultaneously at multiple shipyards under a modular construction model.

A Modular, Multi-Yard Approach

The Gato do Mato project broke with MODEC's conventional practice of constructing a hull at a single yard.

Instead, hull sections were fabricated in parallel at different shipyards, an approach intended to make effective use of available shipyard capacity and provide greater flexibility in project execution.

According to MODEC, the model is designed to take hull construction off the critical path of a typical deepwater project. When paired with the company's Next Generation Hull design, the approach is meant to support the efficient delivery of increasingly complex offshore developments.

The company stated that learnings from this first application of the model will be reflected in future projects.

Mating Work Completed Early With 99% Acceptance Rate

Floating-stage hull mating and welding for the vessel began in October 2026. MODEC reported that the above-water hull mating was completed one week ahead of schedule, with a 99% acceptance rate recorded in dimensional-control inspections.

In late October, the vessel moved into dry dock to carry out the remaining scope of work.

That scope includes underwater hull welding, installation of the riser support structure, dimensional-control checks, riser drift tests, and cover-removal tests.

Dimensional Control Across Yards Was the Key Challenge

Soichi Ide, Head of MODEC's Floating Production Solutions Business Unit, said early engagement with the company's partners and close coordination with the client through months of preparation were key to achieving the early completion.

"One of the project's major challenges was maintaining dimensional control across multiple yards," Ide said. "We overcame it by combining the quality management expertise of Japan's shipbuilding industry with the capabilities of COSCO, our Chinese yard partner, developed through a 20-year strategic partnership."

Ide described this integrated approach, supported by rigorous project execution and decades of accumulated know-how, as difficult to replicate and surpass. He also credited the project team with making effective use of favorable weather conditions while maintaining a strong focus on quality, safety, and schedule.

Build-to-Operate Philosophy and the Shell Relationship

Ide emphasized that every step of the project, from design and execution through operations, is focused on delivering a safe and reliable FPSO, reflecting MODEC's Build-to-Operate philosophy.

"The FPSO Gato do Mato - Orca project demonstrates the distinctive value of this project execution approach and purpose-built hull design, which we look forward to presenting to our customers," Ide said.

"I would also like to thank Shell for placing its trust in MODEC and in this approach and for being the first customer to adopt it."

Shell is the client for the FPSO Gato do Mato project, which is located in Brazil. The vessel joins MODEC's portfolio of floating production systems deployed in Brazilian waters, where the company has built a longstanding presence in the FPSO and FSO sector.

A Reference Point for Future Projects

The early completion of hull mating on the first application of the multi-yard modular construction model gives MODEC a reference point as it pursues future offshore projects.

The company indicated that the purpose-built hull design and construction approach demonstrated on this project will be presented to customers as part of its floating production solutions offering.